Park House School
|
Low Carbon Heating - ASHP Plant and BMS Controls system |
|
|
Project site: |
Park House School, Newbury RG14 6NQ |
|
Client: |
United Learning Trust, London Region 1 |
|
Contract Value: |
£416,834.00 |
|
Contract Type: |
JCT Minor Works Building Contract with Contractor's Design MW2016 |

Strip out works
- Plant room and heat distribution pipework
- Pumps, Fan coil heaters and radiators
Supply and Install
- 2 No 150KW Air Source Heat Pumps
- 2 No 1000Lt Buffer Vessels.
- East and West Wing Twin Invertor controlled Pumps
- ASHP Primary circuit Twin Invertor Pumps
- 19 No. Biddle Fan coil units and 20 Low temp Radiators c/w TRV's
- Distribution Pipework, Fittings, Valves, and Insulation
- Twin Pump Pressurisation unit
- 2 No. 300Lt Expansion Vessels
- Magnetic filtration and dosing pot.
- Electrical Trunking, wiring, Switchgear and earth bonding.
- New lighting with Emergency Luminaires
- Gas Solenoid valve and Gas Detection Alarm Panel
- Complete New Control panel, Trend BMS controls system, c/w 4 No Space Zone Sensors, remote monitoring, and associated equipment
- Builders work in connection with the new installation.
- Acoustic Fencing around ASHP compound to comply with Planning Consent.
- Trenching and laying of 100 Mtr of Pre insulated underground pipework to ASHP base.